A proposal to power Nigerian data centres with gas that would otherwise be flared should begin with the gas supply and the intended workload. Developers should establish what gas they can use, on what terms, before announcing computing capacity.
The World Bank publishes estimates of flaring at individual locations. Its method uses satellite observations of infrared heat to estimate gas volumes.1 A developer can use those records to identify places for further investigation. The developer still needs evidence of recoverable supply at the proposed site.
Kaliabe's Flare Tracker publishes estimates and states their limits. Its methodology distinguishes its satellite-derived estimates from regulatory findings.2 This article sets out the evidence an infrastructure buyer should request after that initial screen. It does not describe a Kaliabe gas or data centre deployment.
Establish access to the gas
The upstream legal route includes a permit for designated flare sites. Regulation 6 of the Gas Flaring, Venting and Methane Emissions (Prevention of Waste and Pollution) Regulations, 2023 provides for a Permit to Access Flare Gas for designated sites. Regulations 9 and 10 address the Commission's and permit holder's obligations. The instrument also defines connection and gas supply agreements.3
Before commissioning a design, a developer should identify the party with authority to supply the gas. Obtain the relevant permit and proposed agreements. Ask counsel to confirm the rights available to the project and any conditions that remain unmet. This discussion concerns upstream flare gas. A project using gas from a processing facility needs its own assessment of the applicable legal route.
The commercial review should establish the supply term and interruption rights. It should also establish who pays for the connection and gas treatment. A project team should price delivered fuel rather than assume that gas currently being flared will be free to use.
Measure supply before sizing the facility
An annual flare estimate is a starting point for a measurement programme. Ask the operator for flow records and gas composition. Check pressure at the intended connection point. Investigate changes during maintenance and production interruptions.
The engineering team should size generation against the supply it expects to have during those conditions. It should then calculate the power needed for cooling and other facility equipment. The IT capacity is the power available to servers after those requirements have been met.
At this stage, publish the assumptions alongside any capacity estimate. State the period covered by the measurements. Explain how the design would respond to a loss of gas. A capacity estimate without those conditions is incomplete.
Choose the workload before the location
A buyer should specify how long a workload can stop and how quickly staff must restore it. The developer can then compare that requirement with the proposed power system and network connections.
A hypothetical buyer running batch jobs might accept scheduled interruptions. A payments institution would need to assess the interruption against its own service obligations. The same power proposal should not be assumed suitable for both.
Compare placing computing equipment near the gas with moving gas or electricity to a more suitable facility. Survey the network routes and access roads for each option. Check flood exposure and the practical arrangements for equipment maintenance. Choose the location against the intended service, rather than the apparent size of the flare.
Define the decision to proceed
The next investment decision should depend on a documented gas supply and a buyer's workload specification. The team should also have a site assessment and a costed design that addresses supply interruption.
Where those inputs are missing, fund the investigation needed to obtain them. A proposed pilot should test whether the measured fuel supply can support the buyer's agreed service. The developer and buyer should agree the test and acceptance conditions before equipment is ordered.
Sources
-
World Bank, Global gas flaring data, the individual flare-site volume data and the description of the estimation method. Accessed 26 November 2026. The published volumes are estimates derived from satellite observations. Return to text
-
Kaliabe, Flare Tracker methodology, independence note, section 1 (Detection layer), section 2 (Volume estimation). Accessed 26 November 2026. Cited for the distinction between screening estimates and findings, not for its penalty calculations. Return to text
-
Federal Republic of Nigeria, Gas Flaring, Venting and Methane Emissions (Prevention of Waste and Pollution) Regulations, 2023, S.I. No. 47 of 2023, regulations 6, 9, 10 and 25. Official Gazette No. 125, 12 July 2023. Accessed 26 November 2026. This is the completed Gazette copy hosted by FAOLEX. Return to text